The BCUC's Alternative to Site C
The BC Utility Commission (BCUC) released for comment what it
considers to be an alternative to Site C that could meet future electricity requirements.
Its alternative basically consists of a lot of wind projects, utility scale batteries and conservation
measures. Based on a number of assumptions, it estimated the present value net costs
that this alternative would entail (with all expenditures and export revenues discounted
back to an equivalent 2018 value taking the time value of money into account).
The BCUC release relates to the fourth question in the Site C terms of
reference about whether there is an alternative to Site C that could provide
the same benefits at equal or lower cost.
There is no explicit comparison to Site
C in the BCUC release, as it does not provide a comparable Site C 2018 present
value cost net of export revenues. However, BCUC’s estimates would appear to
suggest that contrary to BC Hydro’s calculation that an alternative portfolio of
projects would be some $7 billion in present value more costly for ratepayers, its
alternative could be equal or less expensive. It will be very important for
government to know exactly why there is such a huge difference in results.
In this truncated hearing process that
the government established for Site C, there is very little time and
opportunity to question and challenge the assumptions and analysis that BC
Hydro, other parties and in this case the BCUC itself has brought forward for
consideration. The BCUC has provided less than one week to comment on what it
just released. This is very problematic --- particularly so in this case given
the importance of what BCUC has put forward and the many questionable
assumptions it has made.
The BCUC alternative relies heavily on
wind power and it assumes BC Hydro could integrate some 600 MW of wind at half the
integration cost per MWh that BC Hydro assumed, based on concerns expressed about
BC Hydro's estimate. Whether those concerns and an arbitrary reduction of wind
integration costs by 50% are valid are matters that require careful
examination.
BCUC assumes that the wind projects in
its alternative will provide a significant amount of dependable peak generating
capacity (26% of the nameplate capacity) despite its assumption that all of the
wind projects would be located in the same general area to avoid transmission system
upgrade costs. But BC Hydro has to plan on the basis of what it can rely on,
and it can’t rely on the wind blowing exactly when the power is needed. Overall
BCUC asserts that its combination of wind, batteries and conservation measures can
provide the same reliability as Site C without any technical studies to confirm
what can only be described as a very questionable proposition.
With respect to the cost of the conservation
measures, BCUC considers only expenditures BC Hydro would have to make for
programs and incentives. It doesn’t take into account the generally much larger
cost that customers themselves have to pay to achieve the energy reductions –
in other words it fails to measure the full cost of a key component of its
alternative to Site C.
BCUC assumes a very low export price
for surplus energy and no value for surplus peak generating capacity; it
completely ignores the possibility of sales and greater coordination with
Alberta. And it doesn’t consider or discuss any differential between the export
value of surplus from Site C and surplus from its alternative scenario. It says
there will be no seasonal storage and shaping benefits from the Site C
reservoir, but ignores the shaping
benefits Site C will realize from the upstream Williston reservoir – a key reason why BC Hydro has wanted to
develop Site C over so many years.
BCUC arbitrarily reduces on a prorata basis
the cost of its alternative when it produces more energy or capacity than Site
C and is needed for meeting domestic load. The more appropriate adjustment
would have been to reduce import costs.
BCUC assumes all of the wind and
battery installations will be undertaken and financed by BC Hydro. It is more likely
that a large part of this would be undertaken by IPPs with higher financing
costs built into their bid prices.
BCUC asserts the GHG impacts would be
the same with its alternative and Site C but it did not consider the amount and
social value of the displacement of thermal production and reduction of GHGs in other jurisdictions resulting from surplus sales. This displacement of thermal and reduction of GHGs would be
much greater with Site C than its alternative.
Most importantly, BCUC does not address
the marked differences in uncertainty and risk with its alternative as compared
to what is known about Site C — uncertainties not only with respect to cost and
performance but also environmental impacts, land base and siting, First Nation consultation
and regulatory constraints.
Hopefully some of these issues will be
addressed and corrected in the few remaining weeks of the hearing. But in any
event, in the end the government will have to decide in what agency it has most
confidence and what kind of future it wants for BC Hydro – to develop and
enhance the comparative advantage British Columbia has had with its hydro system, or develop more
wind with battery back-up and encourage more conservation as other
jurisdictions moving off fossil fuels have been forced to do.
I learned long ago that it is unwise to comment on things that you don't fully understand. Such is the case for me here. If, as Dr. Shaffer, suggests, there are errors and inconsistencies in the BCUC staff's PV analysis of alternatives to Site C, then I would agree these should be corrected or explained to achieve a "level playing field" for a PV comparison with Site C. However, the BCUC staff analysis does demonstrate an interesting trend with load forecast assumptions. That is, the change in PV for the alternative scenario, in moving from the BCH's high to low forecast, is a reduction of almost 50%. I doubt that the change for the Site C PV would be anywhere near as dramatic for the same change in load forecast. A number of parties to the proceeding have suggested that BCH's load forecasts are much too high, and that a projection of flat load growth (or even declining) may be more realistic given trends seen in other jurisdictions (and the fact that BCH's own load growth has been relatively flat for 10 years). So yes, let's correct any errors and inconsistencies in the BCUC staff PV analysis, but let's also look at the issue of whether lower load growth could sway the decision away from proceeding with Site C.
ReplyDeleteGraeme Simpson, P. Eng.